PSA Road Repair 11-4-22

Public Notice: Constructors Inc. will be paving Boyd Dr. from Juarez St. (N. of the intersection) to Radio Blvd. on Monday November 7, 2022, which will complete the Boyd Dr. project paving. The crews are waiting for the school buses to run before they  begin the paving. They will allow the residents in and out that live in that section of Boyd Dr. Juarez St. will be open to thru traffic. Radio Blvd. Boyd Dr. and Monterey St. traffic will be detoured to either San Jose Blvd. or Standpipe Rd

Also, Monday November 7, 2022, Constructors Inc. will begin the Edge Milling process on Westridge Rd… The entire Westridge Rd. is going to be edge milled and overlayed.

milling will take place Nov. 7 and 8 and paving will take place Nov. 9 and 10, with the hope of completing Westridge by Nov. 11.

 

 