This is the second part of our development report, which is compiled by our Planning and Regulation Department. This report has been shortened significantly in order to meet print requirements. The second portion will cover residential developments:

RESIDENTIAL DEVELOPMENTS

Cielo Lindo Subdivision Phase 2A: plans are being finished to extend Phase 2 of the Cielo Lindo Subdivision to add 15 new residential lots to the development.

Martin Farms Subdivision Unit 4: located to the north of Martin Farms Subdivision Unit 3, east of Old Cavern Hwy. Unit 4 will create 66 new residential lots for development. This item is scheduled to appear before the Planning and Zoning Commission at the February 7, 2022, meeting for consideration. Construction plans are being developed.

Oasis Subdivision Phases 1-3: located to the north of Farmview Subdivision Phases 1-4, and east of Martin Farms Subdivision. The developer is Ken Thurston. Final plans have been submitted have been approved. Infrastructure and drainage dirt work is underway. This project will create 290 new single family residential lots when complete. Phase 1 of the project will be 135 new single family lots and is complete. Work on Phases 2 and 3 has begun and these phases will create 155 new lots.

Carlston Ranch Master Planned Community: located south of Derrick Rd. on the east side of National Parks Hwy. The developer has submitted preliminary drawings for two residential subdivisions that would create 310 residential lots for sale. These plans are in the early development stages.

Ridgecrest Subdivision: located on E. Greene St., 11 undeveloped lots are being built on or marketed currently. The owner of the lots is Ray Westall. The developers and builders are Wanda Welch and Betty Blea. The plan is to build out the remaining lots that have been approved, and then begin work on subsequent phases of this subdivision that will develop the remaining portion of the Westall property. Houses are currently being built.

Arrowstone Apartments: located at the intersection of Hidalgo Rd. and Boyd Dr. This will create 132 new apartment units. The owner/contractor is Crestline Building Corporation. This project is 75% complete. Valuation is $13 million. Phase 1 of this project, which includes 17 apartment buildings, an exercise building, a common building, a pool, and a sand volleyball area, is complete and occupied.

Carlsbad Apartments: located at 301 W. Chapman Rd. Gallardo Construction is the contractor. This will create 120 apartment units. This project is 75% complete. Valuation is $14 million.

Ponderosa Subdivision: located at 3103 Boyd Dr. The owner is Constructors, Inc. Three large commercial parcels will be created along Boyd Dr. for development, as well as a 16 unit employee housing complex to the west of the commercial lots. Constructors plans to house its employees in the employee housing. This project is in the early construction stages.